Tuesday, May 28, 2013

Good news and bad news

The good news: at tonight's board meeting, the Option B gymnasium and related project ($13.0 million) was taken off the table, reverting to the Option A gymnasium project ($12.5 million).


The bad news: the cost has now increased to $13.8 million from $12.5 million.


But the really bad news is that not one single board member asked why the project has increased in cost by $1.3 million in two months, nor was any explanation given.

I am losing what little confidence I had left in the ability of the board to understand, critically examine and question the proposal.

Monday, May 13, 2013

To Receive Notice of Updates to the Blog

If you are not already receiving blog update notices and you want to be added to the update list, click here . No use will be made of your address other than for the updates. Also, click on the "comments" at the bottom of each post to add your own (anonymously if you like) and to read what others have said.

Note:
If you asked to be put on the list and I didn't confirm that I did so, your request may have been deleted as spam. I changed the e-mail address above to prevent deletion so please try again.